In this assignment, write a detailed and specific response to the assigned scenario.
This is an independent assignment where you will apply what you have learned to a real-life project scenario.
Instructions and space to write your responses are also included in the scenario document.
Rewrite assignment named: Oda_Hellesen_Unit 6 Create Risks and Mitigation Measures for a Project Scenario.docx
Assignment scenario named: Risk Response Scenario Assignment in Unit 6-1.pdf
Original grade: 48/100
Feedback: Risk 1: Why do you expect the CIO to gather requirements and develop the schedule and budget for you? Is the CIO the PM, or is it you? Why do you seem to expect the CIO to do all of the critical PM work?
Risk 2: A constraint, by definition, isn’t a risk–it’s an existing trait of the project. I discussed this plenty in class.,
Risk 3: Why is the CIO doing PM work here, too? With the CIO doing all of the work, why does she need you at all?