Materials Management
Worldwide Can-Openers, Inc., makes a family of two hand-operated can openers. The production plan is based on months. There are 4 weeks in this month. Opening inventory is 2000 dozen, and it is planned to increase that to 4000 dozen by the end of the month. The MPS is made using weekly periods. The forecast and projected available balance for the two models follow. The lot size for both models is 1000 dozen.
- Calculate the production plan (list quarterly production)
- Create an MPS (List when scheduled receipts will exist; what periods?)
- What is your projected available balance in Period 3?
Are you struggling with your paper? Let us handle it - WE ARE EXPERTS!
How our paper writing service works
It's very simple!
-
Fill out the order form
Complete the order form by providing as much information as possible, and then click the submit button.
-
Choose writer
Select your preferred writer for the project, or let us assign the best writer for you.
-
Add funds
Allocate funds to your wallet. You can release these funds to the writer incrementally, after each section is completed and meets your expected quality.
-
Ready
Download the finished work. Review the paper and request free edits if needed. Optionally, rate the writer and leave a review.